01 April 2008

Aurbus Still Has Issues with A380 Schedule

For those of you who have followed this, the delays are specific to issues with the wiring harness, and the first airframe with the new harness, MSN26, is expected to be powered up this week, but this is still about three months late, which makes it very difficult for Airbus to hit its target of 13 aircraft deliveries for the year.

Their eventual goal is 4 aircraft a month.

0 comments :

Post a Comment